Below is a spreadsheet showing the plan that the Board supposedly relied on in authorizing the $90 million.  The right hand column reflects my personal views.  Ask yourself as to each item whether it will do much to improve the education that students receive and whether the money would be better spent on items such as more teachers or better use of computers.

 

Analysis of Cost Estimates Used to Justify $90 Million Bond
(based on official report to Board of Education dated 11/20/01)
     
   Estimated   
Description  Cost  Comments
     
1.  Current modernization    
  program.    
1.1  Completion of existing  $    9,000,000 Items 1.1 and 1.2 are troubling,
  contracts from prior   but I would support a smaller
  modernization program.   bond that would cover these
    items.  As explained in my
1.2  Completion of Building  $    9,000,000 statement of November 27,
  B at Beverly Vista   2001, it appears that the 
    District will end up
    approximately $56 million
    over budget for projects that
    were budgeted in 1998 at
    $77 million.  This is deplorable,
    but I do not believe that the 
    students should be deprived
    of these legitimate projects
    because of the mistakes and
    incompetence of the adults
    who bungled this.
     
2.  Life Safety & Security.    
     
2.1  Repair uneven patio  $       112,176 This item is legitimate, but 
paving stones & railings   overpriced.  The official estimate
at main entrance at    shows "hard costs" (actual
Horace Mann School.   construction costs) of $81,910
    and "soft costs" (design and 
    administration costs) of $30,266.
    This is a repair of existing 
    paving/railings, and $30,266 
    seems outrageous for soft costs, 
    even assuming that this includes 
    a historical consultant.  Also,
    I am sceptical about the $81,910.
     
2.2  Americans with   $       500,000 The official explanation states
  Disabilities Act ("ADA")   that the "[b]udget amount is
  Upgrades.   for unforseen mandated 
    upgrades, but not for systematic
    implementation of the District
    ADA Transition Plan."  
    The original $77 million was
    supposed to address this,
    but recent history has shown 
    that the District is capable of
    bungling away millions of dollars
    due to "unforseen" expenses.
    By proceeding based on cost
    estimates that were developed
    on a rush basis to get on the
    March ballot (and that were 
    adjusted based on the preferences
    of particular Board members),
    the District is heading for
    millions of dollars of ADDITIONAL
    "unforseen" costs.  
     
2.3  Upgrades to smoke  $       922,653 This item was SUPPOSED to
  & fire alarm systems.   be included in the original 
    $77 million of projects, but
    now we are told that ADDITIONAL
    upgrades are desirable.  Such
    upgrades include $248,938 of
    "soft costs" and an INCREDIBLE
    $126,037 for smoke detectors in
    the attic of Building A at 
    Hawthorne School.  I believe
    that some of this may be 
    legitimate (at lower prices), but someone
    would need to investigate why this was
    not handled as part of the 
    first round of construction, when
    we were told that all important
    items were being taken care of.
     
2.4  Hazardous materials  $       500,000 This was presented to the Board
  abatement.   as a plug number to cover
    the asbestos abatement that
    will result from some of the 
    other work described below,
    such as adding more emergency
    lighting than was added in
    the initial round of construction.
    Because I believe that virtually
    all of such items are questionable,
    I believe that this number is
    far too high.
     
2.5  Lighting -- Exit &  $    1,207,723 If this was not part of the original
  Emergency.   $77 million project (which has 
"Corridor and exit-way   ballooned into $126 million
  lighting and lighted exit   according to the District's official
  signs that light the way   numbers), I might believe that
  to exits in the event of   this is legitimate.  I would also
  an emergency or power   note that this includes $325,852
  outage."   of soft costs, which seems like
    a lot to pay for supervising 
    the fixing of problems that we
    already paid a lot of money to
    fix.  
     
2.6  Lighting -- Security.  $    1,874,817 Virtually all of this would go to
    the High School, including
    $510,069 of hard costs to replace
    the lighting for a 2 story parking
    garage, and $807,047 of hard
    costs for "exterior lighting
    improvement."  There is also
    $505,838 to design and supervise
    these ridiculously overpriced
    hijinx.  Also, there was ZERO 
    discussion of the future impact
    on the District's electric bill,
    or of the fact that for several
    months the automatic lighting
    systems at the high school were
    coming on over 3 hours before 
    dusk.  Every one of these new 
    fixtures will have a future energy
    cost and maintenance cost.  Also,
    to verify how bogus this is, please
    walk the high school when its 
    dark.  There's nothing wrong
    there that could not be fixed with