|
Analysis of Cost Estimates Used to Justify $90 Million Bond |
|
(based on official report to Board of Education dated 11/20/01) |
| |
|
|
| |
Estimated |
|
|
Description |
Cost |
Comments |
| |
|
|
|
1. Current modernization |
|
|
|
program. |
|
|
|
1.1 Completion of existing |
$ 9,000,000 |
Items 1.1 and 1.2 are troubling, |
|
contracts from prior |
|
but I would support a smaller |
|
modernization program. |
|
bond that would cover these |
| |
|
items. As explained in my |
|
1.2 Completion of Building |
$ 9,000,000 |
statement of November 27, |
|
B at Beverly Vista |
|
2001, it appears that the |
| |
|
District will end up |
| |
|
approximately $56 million |
| |
|
over budget for projects that |
| |
|
were budgeted in 1998 at |
| |
|
$77 million. This is deplorable, |
| |
|
but I do not believe that the |
| |
|
students should be deprived |
| |
|
of these legitimate projects |
| |
|
because of the mistakes and |
| |
|
incompetence of the adults |
| |
|
who bungled this. |
| |
|
|
|
2. Life Safety & Security. |
|
|
| |
|
|
|
2.1 Repair uneven patio |
$ 112,176 |
This item is legitimate, but |
|
paving stones & railings |
|
overpriced. The official estimate |
|
at main entrance at |
|
shows "hard costs" (actual |
|
Horace Mann School. |
|
construction costs) of $81,910 |
| |
|
and "soft costs" (design and |
| |
|
administration costs) of $30,266. |
| |
|
This is a repair of existing |
| |
|
paving/railings, and $30,266 |
| |
|
seems outrageous for soft costs, |
| |
|
even assuming that this includes |
| |
|
a historical consultant. Also, |
| |
|
I am sceptical about the $81,910. |
| |
|
|
|
2.2 Americans with |
$ 500,000 |
The official explanation states |
|
Disabilities Act ("ADA") |
|
that the "[b]udget amount is |
|
Upgrades. |
|
for unforseen mandated |
| |
|
upgrades, but not for systematic |
| |
|
implementation of the District |
| |
|
ADA Transition Plan." |
| |
|
The original $77 million was |
| |
|
supposed to address this, |
| |
|
but recent history has shown |
| |
|
that the District is capable of |
| |
|
bungling away millions of dollars |
| |
|
due to "unforseen" expenses. |
| |
|
By proceeding based on cost |
| |
|
estimates that were developed |
| |
|
on a rush basis to get on the |
| |
|
March ballot (and that were |
| |
|
adjusted based on the preferences |
| |
|
of particular Board members), |
| |
|
the District is heading for |
| |
|
millions of dollars of ADDITIONAL |
| |
|
"unforseen" costs. |
| |
|
|
|
2.3 Upgrades to smoke |
$ 922,653 |
This item was SUPPOSED to |
|
& fire alarm systems. |
|
be included in the original |
| |
|
$77 million of projects, but |
| |
|
now we are told that ADDITIONAL |
| |
|
upgrades are desirable. Such |
| |
|
upgrades include $248,938 of |
| |
|
"soft costs" and an INCREDIBLE |
| |
|
$126,037 for smoke detectors in |
| |
|
the attic of Building A at |
| |
|
Hawthorne School. I believe |
| |
|
that some of this may be |
| |
|
legitimate (at lower prices), but someone |
| |
|
would need to investigate why this was |
| |
|
not handled as part of the |
| |
|
first round of construction, when |
| |
|
we were told that all important |
| |
|
items were being taken care of. |
| |
|
|
|
2.4 Hazardous materials |
$ 500,000 |
This was presented to the Board |
|
abatement. |
|
as a plug number to cover |
| |
|
the asbestos abatement that |
| |
|
will result from some of the |
| |
|
other work described below, |
| |
|
such as adding more emergency |
| |
|
lighting than was added in |
| |
|
the initial round of construction. |
| |
|
Because I believe that virtually |
| |
|
all of such items are questionable, |
| |
|
I believe that this number is |
| |
|
far too high. |
| |
|
|
|
2.5 Lighting -- Exit & |
$ 1,207,723 |
If this was not part of the original |
|
Emergency. |
|
$77 million project (which has |
|
"Corridor and exit-way |
|
ballooned into $126 million |
|
lighting and lighted exit |
|
according to the District's official |
|
signs that light the way |
|
numbers), I might believe that |
|
to exits in the event of |
|
this is legitimate. I would also |
|
an emergency or power |
|
note that this includes $325,852 |
|
outage." |
|
of soft costs, which seems like |
| |
|
a lot to pay for supervising |
| |
|
the fixing of problems that we |
| |
|
already paid a lot of money to |
| |
|
fix. |
| |
|
|
|
2.6 Lighting -- Security. |
$ 1,874,817 |
Virtually all of this would go to |
| |
|
the High School, including |
| |
|
$510,069 of hard costs to replace |
| |
|
the lighting for a 2 story parking |
| |
|
garage, and $807,047 of hard |
| |
|
costs for "exterior lighting |
| |
|
improvement." There is also |
| |
|
$505,838 to design and supervise |
| |
|
these ridiculously overpriced |
| |
|
hijinx. Also, there was ZERO |
| |
|
discussion of the future impact |
| |
|
on the District's electric bill, |
| |
|
or of the fact that for several |
| |
|
months the automatic lighting |
| |
|
systems at the high school were |
| |
|
coming on over 3 hours before |
| |
|
dusk. Every one of these new |
| |
|
fixtures will have a future energy |
| |
|
cost and maintenance cost. Also, |
| |
|
to verify how bogus this is, please |
| |
|
walk the high school when its |
| |
|
dark. There's nothing wrong |
| |
|
there that could not be fixed with |
|